SGP South was Arrow’s first development area, with construction commencing in the Dalby region in 2020.
Our plans for SGP South include around 2,000 wells, to be constructed over several phases.
Further development is planned over the coming years in the Dalby, Kogan, and Hopeland regions and surrounds.
Further south in the Cecil Plains region, we are in the early stage of our plans.
Project plan as at September 2024
Project Area Overview
Area | Dalby, Kogan, Hopeland, Halliford, and Cecil Plains regions |
Number of wells planned | Approximately 2,000 |
Number of Arrow wells in production (as at June 2024) | 250 |
Construction timeline | 2020 - 2037 |