We are planning to expand our operations to an area near Miles from 2025, subject to approvals.

Our plans for SGP North include up to 450 gas wells, a field compression station, a hybrid power plant (solar, battery, and gas), and road and intersection upgrades.

Project plan as at September 2024

Project Area Overview

Area

North-east of Miles

Number of wells planned

450

Number of Arrow wells in production (as at June 2024)

0

Construction timeline

2025 - 2029