Our Surat Gas Project North development, located north‑east of Miles in Queensland’s Western Down, began in late 2024.
As the second major development area within the broader Surat Gas Project, it is already delivering meaningful economic and social benefits to the communities of Miles, Chinchilla and Wandoan.
Working in partnership with around one hundred local graziers and landholders, we’re developing the gas wells and gas production facilities that will supply up to 130 terajoules of gas per day.
We’re proud to be working alongside the people who know the region best, ensuring responsible development that delivers lasting local benefits.
Our local contribution to date
Local community investment
Direct spend with Miles businesses
Jobs created
Surat Gas Project North Fast Facts
Natural gas wells planned over two stages
Terajoules of natural gas per day when fully operational
First gas delivered
Surat Gas Project North timeline
2024
August
Arrow announced expansion of Surat Gas Project to development area near Miles
2024
Late 2024
Early works begin
2025
April
Major works commence
2025
November
First gas delivered
2026
June
100 wells drilled