Arrow is currently undertaking the following activities.

Surat Basin

AreaLocationActivityDate
01 Cecil Plains Cecil Plains
  • Well decommissioning and rehabilitation (south of Cecil township)
  • Baseline assessment of water bores (as required by the Underground Water Impact Report)
From February 2025
02 Columboola Approximately 10 kilometres north-east of Miles
  • Preliminary development work including property turnouts and scoping activity for upcoming works
  • Gravel haulage for access tracks and civil earthworks on Girrahween property
  • Construction of well pads and access tracks north of the Warrego Highway, drilling wells from May 2025
From January 2025
03HookswoodApproximately 10 kilometres east of Miles
  • Facility and pipeline construction, south of the Warrego Highway
From February 2025
04 Daandine  Approximately 25 kilometres north-west of Dalby
  • Well maintenance activities
  • Civil construction (at water treatment facility)
  • Maintenance shutdown, including safety flaring of gas, Thursday 3 April
  • Power station maintenance activity
From January 2025
05BroadwaterApproximately 20 kilometres south-west of Dalby
  • Well maintenance activities
From March 2025
06 Grassdale Approximately 30 kilometres southwest of Dalby
  • Well decommissioning and rehabilitation
  • Well maintenance activities
  • Construction of property turn outs, well pads and access tracks, drilling wells from April 2025
From March 2025
07 Kogan North Approximately 35 kilometres north west of Dalby
  • Well decommissioning and rehabilitation
  • Intersection upgrade - Braemar Warra Road and Dalby Kogan Road
From January 2025
08 Springvale Approximately 20 kilometres south of Dalby
  • Construction of beneficial water network, including testing and comissioning of pipelines
  • Hennings Connection Road upgrade
  • Construction of property turn outs, well pads and access tracks, drilling wells from May 2025
  • Site preparation for short-term accommodation
From January 2025
09 NandiApproximately 15 kilometres south-west of Dalby
  • Construction of beneficial water network, including testing and comissioning of pipelines
  • Construction of well pads and access tracks, drilling wells
From March 2025
10Various areasBetween Dalby and Chinchilla
  • Decommissioning of landholder water bores carried out as per Arrow's obligations under the Water Act 2000 - Kupunn, Brigalow.
From May 2025

Bowen Basin

AreaLocationActivityDate
01 Wards Well Approximately 50 kilometres north of Moranbah
  • 3D Seismic survey of underground rock formations
From October 2024
02 Bowen ATP1103 North of Moranbah, various locations 
  • Drilling exploratory wells
  • Well decommissioning and rehabilitation
From October 2024
03 Norwich Park ATP1031  South-east of Moranbah
  • Well decommissioning and rehabilitation
From January 2025

Activity schedule may vary depending on a number of factors, including weather.