Arrow is currently undertaking the following activities.

For more information about our activities, call us on 1800 038 856 or email info@arrowenergy.com.au.

Surat Basin

AreaLocationActivityDate
Cecil Plains South of Cecil township Well decommissioning and rehabilitationJanuary 2025
ColumboolaApproximately 10 kilometres east of MilesPreliminary development work including property turnouts and scoping activity for upcoming works
Gravel haulage for access tracks and civil earthworks on Girrahween property
January 2025
Daandine  Approximately 25 kilometres north-west of Dalby Well maintenance activities
Civil construction (at water treatment facility)
January 2025
Grassdale Approximately 30 kilometres southwest of Dalby Well decommissioning and rehabilitation
Construction of pads and tracks
Well maintenance activities
January 2025
Kogan North Approximately 35 kilometres north west of Dalby Well decommissioning and rehabilitationJanuary 2025
Stratheden         Approximately 20 kilometres west of Dalby Well decommissioning and rehabilitationJanuary 2025
SpringvaleApproximately 20 kilometres south of DalbyConstruction of beneficial water network
Hennings Connection Road upgrade
January 2025

Bowen Basin

AreaLocationActivityDate
Wards Well Approximately 50 kilometres north of Moranbah 3D Seismic survey of underground rock formations from October 2024
Bowen ATP1103 North of Moranbah, various locations  Drilling exploratory wells
Well decommissioning and rehabilitation
from October 2024
Norwich Park ATP1031  South-east of MoranbahWell decommissioning and rehabilitationfrom January 2025

Activity schedule may vary depending on a number of factors, including weather.